PERTH'S LEADING EARTHWORKS CONTRACTOR

Lot 10 Hyne Road

Lot 10 Hyne Road
  • PROJECT
    Lot 10 Hyne Road
  • CLIENT
    Meyer Shircore
  • LOCATION
    South Guildford, WA
  • DURATION
    May 2013 – July 2013

Lot 10 Hyne Road

The project involved the stripping, proof compaction and import fill of the future office / yard in South Guildford. Unexpected additional topsoil / peat and rubbish was identified on site. Through early identification and discussion with the client, GMF were able to mitigate additional costs.  Large movements of trucks were successfully controlled and no disruptions or complaints were raised throughout the import fill process which saw approximately 3,000 tonne per day delivered to site.

PROJECT QUANTITIES
  • 20,000m² clearing and topsoil stripping
  • 25,000 tonnes import, place and compact fill
  • Final trim of 14,000m² pad areas
  • Shape and trim 150m existing batters
  • Removal of 800m³ topsoil / peat material off site

.

PROJECT ACHIEVEMENTS

Through the use of our integrated health, safety, quality and environmental management systems, GMF achieved project completion ahead of program with zero NCR’s safety incidents.