Toodyay Rd & Railway Pde Road Upgrades

GMF were engaged to upgrade Toodyay Rd to allow for 2.6km of new overtaking lanes and turning lanes in addition to the extension of Railway Pde connecting a recently installed bridge over Ellenbrook River.                                                            The works involved bulk earthworks and the import of fill to build up either side of bridge including backfilling abutments. The critical risks associated with the project were high voltage overhead powerlines, heavy traffic, MRWA and local residents.

 

PROJECT STATS

  • 86,000m² topsoil strip with 34,000m² reused
  • 62,000m² of new roads constructed
  • 400m of drainage pipe & associated 25 pits
  • Removal of 3,000m³ of alluvium contaminated material
  • 13,000m³ earth moved
  • 2km of reshaping and forming new table drains, V drains and E drains.

 

PROJECT ACHIEVEMENTS

GMF completed the full scope of works with zero accidents or incidents. Through strong liaison with the City of Swan, no complaints or delays to completion were incurred. Little to no dust pollution was critical to the project with existing housing and residents in a very close proximity to the work.

 

Jane Brook Subdivision Stage 2A

The project involved the creation of new lots to add to the existing stage 1 of Jane Brook subdivision. The scope of works was everything from undergrounds to roadworks and retaining walls. Following another contractor completing stage 1, strict dust suppression was critical for stage 2A as our client had previously received a number of complaints from residents regarding dust.

 

PROJECT STATS

  • 16,000m³ of earth moved including import of 6,000m³ fill
  • 1.3km of underground water, sewer, drainage and electrical cable & pipe laid
  • 800Lm of retaining walls created using more than 10,000 limestone blocks laid
  • 300m of kerbing laid by GMF subsidiary – Metro Kerbing
  • Negligible dust pollution throughout the project

 

 

PROJECT ACHIEVEMENTS

GMF completed the full scope of works with zero accidents or incidents. Through strong liaison with the City of Swan, no complaints or delays to completion were incurred. Little to no dust pollution was critical to the project with existing housing and residents in a very close proximity to the work.

Tapping Subdivision Stage 1, 2 & 3

Completion of 70 lot subdivision for Niche. This project is in close proximity to GMF subsidiary CCR’s northern recycling yard. GMF were able to export any unsuitable material/excess offsite to our CCR yard. Scope included Bulk Earthworks, underground services including drainage cells and sewer main connections along with asphalt, base, kerbing, retaining walls and concrete footpaths.

PROJECT STATS

  • 3000m² new full depth pavement and asphalt
  • 350m new retaining walls
  • Earthworks moving more than 15,000m3
  • 800m of kerbing laid
  • Supervision of all associated underground services

 

PROJECT ACHIEVEMENTS

GMF completed the full scope of works with late additions within the initial project program presented. Consistent liaison with the City of Wanneroo was required to ensure that there were no complaints or delays. The project was carried out with zero accidents or incidents and Stage 1 led to the award of Stages 2 & 3.

High Wycombe Station

Over the past couple of months, our Civil division has been busy working at the Forrestfield-Airport Link at the new High Wycombe Station for the Salini Impregilo-NRW JV.

The upgrades feature road and carpark construction to service the new High Wycombe Station which forms part of the Forrestfield-Airport Link Project.

Works are expected to be complete later in 2021.

 

PROJECT STATS

  • 15,000m² new full depth pavement and asphalt
  • All relevant associated drainage works to suit
  • 3km of kerbing to be laid
  • 3,000m2 of pedestrian shared paths

 

John Forrest Footpath Upgrades

GMF was engaged by the Department of Biodiversity, Conservation and Attractions (DBCA) to upgrade the existing footpath which is the beginning of many walking trails throughout the scenic John Forrest National Park. The upgrades include minor drainage work as well as importing gravel before priming the surface and asphalting.

PROJECT STATS

  • 1,000m² new pavement, prime and asphalt
  • New drainage to maintain water flow into the weir
  • New shoulder and access track installed
  • 4 concrete footing bridge abutments installed

..

PROJECT ACHIEVEMENTS

GMF Civil managed the project ensuring that pedestrian (and wildlife) traffic still has access to the beautiful walks that the Park has to offer. We  worked safely in an environment with tricky access to stay within time constraints before the busy Easter period influx of visitors to the Park.

Mundaring Waste Water Treatment Plant

GMF completed bulk earthworks and roads under strict environmental and safety standards, for the development of the Mundaring Waste Water Treatment Plant. Initial works involved the large clearance of dense forest area, including large trees and the stripping of 200 millimetres of topsoil over the entire site area.

Our team cautiously moved over 100,000 cubic metres of clay / silty soils from the site, constructed five pad areas and multiple drying beds. Second stage of works included the construction of an overflow sump and implementation of stormwater drainage systems. Road works surrounding the treatment plant were also awarded to GMF on the back of the successful completion of our forward works. Works consisted of all pavement base works and wearing courses.

.

PROJECT QUANTITIES
  • 13.6ha of clearing and topsoil stripping
  • 110,000m³ earthworks cut to fill
  • 65,000m² final pad trimming
  • Supply and install 10,000m² HDPE Liner
  • 1km of stormwater drainage (525-675mm pipe)
  • 15,000m² new road pavement
  • Pilling mats
  • Bitumen paving and kerbing

.

PROJECT ACHIEVEMENTS

GMF easily adapted to the site and provided the client new techniques to achieve project requirements. We successfully completed high compaction of clay material on site whilst simultaneously upholding strict health, safety, quality and environmental requirements. GMF maintained tight deadlines and operational schedules for the duration of the project, able to efficiently manage the introduction of multiple design and specification changes.

Clayton Street Roundabout

GMF provided road construction and kerbing works for the Clayton St Roundabout development. Works included the box out of new and existing subgrade, verge and footpath. Scope involved the demolition of street furniture, footpath, kerbing and asphalt. GMF completed the new and existing widening of road, involving the import and placement of 600 millimetres of road pavement, kerbing and asphalt. To accommodate the new roundabout numerous existing services were relocated and new drainage systems were installed. All works were completed whilst road and footpath was open to the public.

.

PROJECT QUANTITIES
  • 3,000m² pavement construction
  • 500 metres of new kerbing
  • 600m² of brick paving and footpath
  • 12 new drainage structure
  • 250m² of fibre reinforced concrete infil

.

PROJECT ACHIEVEMENTS

GMF successfully completed all works within client time frames and with zero traffic and safety incidents, providing full public access to the road and footpath for the entire duration of the project. Strong stakeholder management and control was involved with the successful completion of works, including ensuring GMF upheld the highest safety and environmental conditions.

Collier Road Roundabout

GMF provided a wide scope of construction works for introduction of the Collier Rd Roundabout. Works included the demolition and disposal of all kerbing, concrete, pavement base, asphalt and landscaping. GMF successfully completed construction works across four operational stages, consisting of profiling the existing road and completing all works alongside high volume traffic. Significant challenges were managed for the completion of this project including stakeholder management and the coordination of local service authorities.

.

PROJECT QUANTITIES

  • 2,000m² pavement construction
  • 1,500m² profiling and pavement base removal
  • 800m² brick paving and footpath
  • Associated drainage and structures
  • 700 metres kerbing works completed by GMF’s subsidiary company METRO Kerbing & Concrete

.

PROJECT ACHIEVEMENTS

Critical stakeholder management was maintained for the successful running of the project, ensuring full access was provided to the public along Collier Rd and zero traffic and safety incidents occurred. GMF was able to mitigate difficulties through the separation of the job into four stages of operations. Our management team successfully coordinated stakeholder relations and local authority requirements for the duration of the project.

11 Lot Subdivision

GMF cleared 3,055m² of top soil and provided a range of bulk earthworks services in preparation for construction of an 11 lot subdivision for Wood & Grieve Engineers. All work carried out incorporated critical traffic management and operational schedules, to enable access along Rockingham Rd. Road construction works carried out included the construction of road, subgrade and finished surfaces, retaining walls, kerbing and concrete services. GMF completed water, sewer, communications and electrical reticulation services to the eleven new allotments.

..

PROJECT QUANTITIES

  • Bulk earthworks cut and fill (Import fill 1,650m³)
  • Final trim 3,055m²
  • New road construction area 1,550m²
  • 267 metres concrete kerbing
  • 489 metre limestone retaining walls (three – seven courses high)
  • 150m² intersection pavement installation
  • Reticulation services to 11 new allotments

.

PROJECT ACHIEVEMENTS

Quality control and management ensured GMF was able to deliver the large scope of works within client timeframes, whilst simultaneously meeting all pertinent local government and authority requirements. GMF successfully managed traffic access to Rockingham Rd with zero traffic or safety incidents and provided dust management and control on site.

Hartman Drive Intersection

GMF Civil provided works for the construction of a new slip lane and intersection on Hartman Drive.  Works included demolition of existing structures and cutting of existing road under high traffic conditions. Road construction included pavement construction of a 225 millimetre thick limestone layer, 75 millimetre ESL road base layer and 35 millimetre asphalt layer. GMF Civil also provided kerbing and footpath works, drainage structures, landscaping and the supply and installation of street lighting and cabling.

.

PROJECT QUANTITIES

  • 1,500m² new pavement including ESL basecourse
  • 250 metres of new semi mountable kerbing
  • 300m² concrete footpath
  • 300 metres of saw cut and tie in works
  • Associated drainage structures and services

..

PROJECT ACHIEVEMENTS

GMF Civil critically managed operations at Hartman Drive to ensure traffic access was still available whilst completing various stages of works. With the implementation of construction stages and health, safety, quality and environmental management systems, we successfully facilitated management of traffic and maintained strict client deadlines.

Lot 10 Hyne Road

The project involved the stripping, proof compaction and import fill of the future office / yard in South Guildford. Unexpected additional topsoil / peat and rubbish was identified on site. Through early identification and discussion with the client, GMF were able to mitigate additional costs.  Large movements of trucks were successfully controlled and no disruptions or complaints were raised throughout the import fill process which saw approximately 3,000 tonne per day delivered to site.

PROJECT QUANTITIES
  • 20,000m² clearing and topsoil stripping
  • 25,000 tonnes import, place and compact fill
  • Final trim of 14,000m² pad areas
  • Shape and trim 150m existing batters
  • Removal of 800m³ topsoil / peat material off site

.

PROJECT ACHIEVEMENTS

Through the use of our integrated health, safety, quality and environmental management systems, GMF achieved project completion ahead of program with zero NCR’s safety incidents.

St John of God Midland

GMF were awarded the bulk earthworks and civil works for the Midland Hospital Campus, including the construction of two hospital entrance roundabouts. Initial works involved the clearing of site followed by installation of stormwater systems, detailed excavation works and construction of retaining walls. GMF successfully completed construction of carpark and kerbing works within the hospital site. Construction works for the two roundabouts on Clayton St and Yelverton Crescent were critically managed to ensure road access was available for the duration of the project.

..

CAPABILITIES INCLUDED:
  • Bulk earthworks
  • Backfilling
  • Roundabout construction
  • Pavement including roadbase and heavy duty asphalt
  • Kerbing
  • Stone pitching and retaining walls

..

PROJECT ACHIEVEMENTS

GMF successfully delivered project requirements whilst maintaining stringent quality standards. We were able simultaneously manage high volume traffic of both hospital entrances and meet our clients’ operational schedules.